Skip to main content

Tokamak Cooling Water System

The US is responsible for 100% of the design, engineering, and procurement of the Tokamak Cooling Water System (TCWS).

ITER’s fusion power will reach 500 MW during the deuterium-tritium inductive plasma operation. Heat will be transferred by the Tokamak Cooling Water System from client systems to the environment through the secondary cooling system. TCWS is designed to cool client systems, such as the first-wall/blanket, vacuum vessel, divertor, and neutral beam injector. Additional operations include baking of in-vessel components, chemical control of water provided to client systems, draining and drying for maintenance, and leak detection/localization.

For more information, contact Kyle Wooley, TCWS Team Leader,  US ITER Project Office, Oak Ridge National Laboratory, wooleyky@ornl.gov | 865-241-4329

 

 

tokamak cooling water piping fabrication

Global team yields efficiencies for tokamak cooling water procurement

A joint TCWS Project Team—composed of staff from the ITER Organization and the US ITER Project Office—is making strong progress in the procurement of the tokamak cooling water system (TCWS).

Source: ITER Newsline

Normal drain tank being lifted into tokamak complex

First US Components Installed in Tokamak Complex

Three drain tanks were the first  US-supplied components installed in the ITER tokamak complex.

Tokamak Cooling Water System Final Design

Tokamak Cooling Water System Final Design Achieved

To remove the heat from the components closest to the plasma, the tokamak cooling water system will rely on over 36 kilometres of nuclear-grade piping and fittings as well as a large number supports, valves, pumps, heat exchangers and tanks—all integrated into the limited space of the Tokamak Complex. The final design review was held successfully held in November 2017 for the elements that need to be in place by First Plasma.

Source: ITER Newsline

Instrumentation and controls system scope for US ITER

Instrumentation and Controls Design Progresses for First Plasma

The I&C team has completed a number of design achievements in preparation of First Plasma deliveries, including: Ion Cyclotron Heating (RF Bldg.) I&C First Plasma Final Design Review (December 2017), Tokamak Cooling Water System I&C First Plasma Final Design Review (November 2017), Vacuum Auxiliary System (03) Conceptual Design Review (July 2017) and Roughing Pumps System I&C Conceptual Design Review (April 2017).

Pipe press at the Schulz XP plant in Robinsonville, MS

35km of Cooling Water Piping in Fabrication

Building a Sun on Earth requires not only extensive heating systems but also large cooling systems for the removal of plasma heat from the tokamak. Fabrication of tokamak cooling water system piping is now underway at Schulz Xtruded Products in Robinsville and Hernando, Mississippi (US), with management oversight by the US Domestic Agency and the ITER Organization.

Source: ITER Newsline

drain tank testing at Joseph Oat Corporation

US delivers multiple “firsts” for ITER site

US ITER is ramping up hardware deliveries to Europe. In January, the United-States delivered its first batch of production conductor for the super-conducting toroidal field magnet system; the US also completed delivery of the first highly exceptional load, a massive high voltage transformer for the steady state electrical system, to the ITER site. In March, the first components of the tokamak cooling water system, two large drain tanks, were shipped from Camden, N.J. for delivery to the ITER site.